Work has begun on the 800 metres of concrete foundations. Trench is dug, shuttered and filled with concrete. It is covered once level, then the covers are covered in sand until the concrete sets. Once the foundations are in the concrete with be drilled and fitted with a 'key way'. Onto this 'key way' the pre-fabricated concrete stair sections will be installed. The installation of these stair sections should start in November 2015.
25th August 2015